On the north side of Wangjiang Road, Shangcheng District of Hangzhou, there is a construction site behind the Hangzhou Local Chronicles Museum, under which lies the Lingshou Palace of the Southern Song Dynasty.
Deshou Palace site is an important palace site in Lin’an City of the Southern Song Dynasty, second only to the Imperial City site. It is an extremely important historical and cultural remains in Hangzhou.
DE shou palace site protection display project and the southern song dynasty museum (phase I) project, to restore the southern song dynasty royal palace construction and jiangnan landscape, rich the audience experience, comprehensive rendering shou palace ruins, linan city ruins and the southern song dynasty economic, cultural, social, unveiled the sleeping for hundreds of years of palace mystery.
At the construction site, thick walls are used around the site project to block the infiltration of groundwater, and TAD water stop curtain technology is comprehensively adopted to ensure that the groundwater level in the hall basin is in a controllable state.
TAD method, also known as “canal cut prefabricated underground continuous wall construction method”, is a method of inserting precast concrete slab in the construction process of water stop seepage wall. The continuous wall under the reinforced concrete land formed by this technology integrates the functions of retaining and water interception, which can effectively protect the site.
The project also uses new technologies such as air cooling and heat pump ventilation system, and strives to achieve accurate control of site protection, so that the site can stand the test of construction, and achieve a win-win situation of protection and display of the site and utilization.
In addition, the project innovatively uses the first-story steel structure and the second-story wood structure in the structural design, laying a foundation for the diversified display of the main building.
All the management personnel of the project department firmly build the awareness of the safety and protection of cultural relics, and strictly control the operation, evaluation and plan of “three no shortage” of the operation activities involving the location of cultural relics.
Master Hu, an electrician of the project, said, ” We often find ‘new’ in the middle of the construction. At this time, we will stop work and let the staff of the cultural relic protection unit come to investigate.
“An old master of the Cultural Heritage Bureau was stationed at the construction site. When the workers dug out something, he first studied it, and took the valuable ones back to the Cultural Heritage Bureau for further” in-depth investigation “.
” As the opening work of Hangzhou to show the ‘Song Yun culture’, this project involves many departments, tight construction period, heavy task and high pressure.
“Liang Shaochun is a project manager with rich construction experience, serving as the” big master ” of the Fushou Palace project.
Speaking of the difficulties encountered in the construction of the project, Liang Shaochun said frankly: ” It is not difficult to do the project. We are always ready for war until the moment of completion.
“As soon as the project started, it encountered a series of” trouble gift packages “. The pile drivers entered the field and found that the ground was all stones, which was different from the original drawings, not only to recontact all parties for exploration, but also to make prefabricated bricks and so on.
At present, the western part of the project is under foundation construction, which will be completed and open to the public before the Asian Games.
Ma Min